Essential resurfacing of BNE’s main runway has been completed after nearly six months of night works involving up to 100 personnel and 60 items of plant and equipment per shift. Around 200,000 work hours and 18,000 tonnes of asphalt have been employed in this project, at an investment of more than $15 million.